Driveway approaches in Temecula CA: the City's piece of your driveway
The approach is the one part of a driveway a Temecula homeowner doesn't design. It sits in the public right-of-way, so the City sets its shape in Standard No. 207, issues an encroachment permit before anyone touches it, and inspects it once it is formed. These are the usual reasons it gets rebuilt. The driveway behind the approach, and the rest of our flatwork, is on the concrete contractor in Temecula CA page.
- The apron has settled and left a trip edge at the sidewalk or a dip at the gutter.
- It has cracked through or broken at the corners from years of turning tires.
- The driveway behind it is being replaced and the old apron no longer lines up.
- The opening has to get wider for a third car or an RV, up to the 30 foot limit.
- A new driveway is being added where there was none, which also needs the City Engineer's approval.
Standard No. 207: what a Temecula approach is built to
The City's Residential Driveway Approach drawing, approved March 30, 2020, fixes almost every dimension. These are the numbers on the sheet.
| Item | Requirement |
|---|---|
| Width at the property line | 12 ft minimum, 30 ft maximum (residential) |
| Thickness | 6 in minimum |
| Concrete | Class 560-C-3250 |
| Slope across the walk band | 2% over 4 ft, then 9% over the last 2 ft to the gutter |
| Curb face at the flow line | 1 in |
| Side wings | 4 ft transitions each side |
| Joints | Weakened-plane joints at 5 ft intervals |
| Between two driveways | 20 ft of full-height curb on one frontage |
| Subgrade | Top 12 in compacted to 95% |
| High-sulfate soil | 6 mil plastic sheeting under the slab |
City of Temecula Public Works, Improvement Standard Drawings 2020, Standard No. 207 (approved March 30, 2020), plan, Section A-A, Detail 1 and notes 1 to 6. Use of the standard is subject to the City Engineer's approval.
Why the sulfate note matters here
Note 4 on the drawing calls for 6 mil plastic sheeting under the approach where the soil next to it has a high sulfate content, because sulfates in the ground attack concrete over time. In the USDA soil survey the highest concrete-corrosion ratings in Temecula fall on the salty creek-bottom soils along Interstate 15; the Temecula soil guide has the sample points.

The encroachment permit, start to finish
The City's Land Development submittal list for a residential or commercial driveway approach asks for five things: the completed encroachment permit application, a driveway exhibit, a certificate of liability insurance, a current state contractor's license and a current City business license. The permit is good for 180 days, and an extension of up to six months is possible on written request, with a permit issuance fee.
The insurance is the step that surprises owners. The application asks for $1 million general and auto liability with the City named as additional insured. Owners of single-family homes doing their own approach can use homeowners insurance with the City named, at the smaller limits the form lists. The Temecula driveway permit guide has the whole sequence.
How an approach is rebuilt, step by step
- 1Apply for the encroachment permit
The application, a driveway exhibit, a certificate of liability insurance, a current state contractor's license and a City business license go to Land Development through the City's online permit portal.
- 2Notify the inspectors
The permit holder emails Land Development Inspection at least two working days before work starts, and a pre-construction meeting is held first, as the application asks.
- 3Saw-cut and remove
The old apron, and any curb or walk panel being replaced, is saw-cut at clean lines and removed; the subgrade is reworked and compacted.
- 4Form and pour to Standard No. 207
Forms set the 2 percent and 9 percent slopes and the side wings; 560-C-3250 concrete goes in at least 6 inches thick with weakened-plane joints every 5 feet.
- 5City inspection and cure
The City inspects every approach in the right-of-way against the approved plan and its standards, and the apron cures before cars go over it.

Approaches outside the city line
East of Temecula in the wine country, the road belongs to Riverside County, so the permit comes from the county Transportation Department instead; its fee table, as archived in October 2025, lists a residential driveway approach at $79 for the permit plus $107 for inspection, $186 in all, and says most permits are issued within 14 working days. South of the county line, toward Rainbow, San Diego County requires a written encroachment permit before work in a county road right-of-way, and a traffic control permit before a residential driveway there is built or repaired. The wine country page covers the rural version.